Current lead time and pricing data for electronic components.

Last Update : 22/03/2007

We are here to help.
If you are being told parts cannot be sourced, don't take NO for an answer!

Lead Times and Pricing Trends

Summary

Micro

Standard lead-time approx 12-16 wks.
Renesas 16 wks.
Maxim 20 wks.
Tosh 16 wks.
TI ahead at only 6-8 wks

 

Commodity Lin & Logic

Maxim 18 wks & Rohm 14 wks +.
STM surface mount back on alloc rest 12 wks.
Standard Lead-time approx 14-16 wks.
FSC offering around 20 wks.
TI extended 26 wks – test problems on most.
All old Burr Brown on alloc

 

Non- Commodity Lin & Logic

Standard Lin & Logic between 12-16 wks.
FSC now stable 12 wks.
TI offering 12-16 wks.
STM surface mount is on alloc rest 12 wks.
AD extended to 16 wks

 

Memory

Standard lead-time 12-20 wks.
STM have gone from alloc to 10 wks.
BEWARE – TOSH now withdrawn. SRAM, NAND chips.

Discretes

FSC have moved out to 22 wks.
INFN are at 12 wks.
STM surface mount is on alloc rest 12 wks.
Vishay 20 wks, some alloc.
All the rest at 12-18 wks.

Other

FSC Opto see Everlight – 8 wks.
Vishay 20 wks, some alloc.
Tosh opto on alloc.

Electrolytics
Standard lead-time is extending to approx. 18 wks.
Pan standard lead-time 18 wks – ask marketing for factory improvement.
Tantalums
Lead-times all over the place on Tants varying from 6-20 wks
Rohm no longer promoting. No quote for to new business.
Some HiCap values are on extended leadtimes up to 20/24 wks.
Vishay 11-16 wks Kemet 6-20 wks
Cap Ceramics
Lead-times now more under control at 8-18 wks
AVX, Kemet & Epcos at only 8-12 wks.
The rest sit at around 12-18 wks.
Kemet & AVX stock can be checked online, please contact us.
Inductors

Lead-times are extending approx. 12-16 wks.
Bourns 12 wks.
Epcos 4-15 wks, often stk 0805’s 9-12 wks.
Tyco at 12 wks.
Murata 10 wks

 

Protection

Lead-times range from 12-16 wks.
AVX & Bourns offering 12 wks.
Epcos 14 wks.

 

Resistors

Lead-times range from 6-16 wks.
Many RN73 (0805 10ppm’s) in stock, leadtime down to 6-8 wks.
Vishay CRCW series are currently 12-14 wks

 

 


Legend:

Increasing ↑  Stable    Decreasing

Last updated: 2nd March 2007
Semiconductors - Standard Products
Technology Supplier Lead Time Price Comments
LOGIC Fairchild Lead Times
8-16 wks
LOGIC NXP   Lead Times
8-12 wks
LOGIC ON Semiconductor Lead Times
8-12 wks
LOGIC STMicroelectronics Lead Times
12-18 wks
LOGIC Texas Instruments Lead Times
6-12 wks
LINEAR National Semiconductor Lead Times
6-12 wks
LINEAR STMicroelectronics Lead Times
8-16 wks
LINEAR Texas Instruments Lead Times
4-8 wks
LINEAR Toshiba  
LINEAR ON Semiconductor Lead Times
6-12 wks
LINEAR Vishay Lead Times
16-22 wks
DISCRETE ON Semiconductor Lead Times
8-12 wks
DISCRETE Vishay Lead Times
12 wks
DISCRETE Taiwan Semi Lead Times
12 wks
DISCRETE STMicroelectronics Lead Times
12-16 wks
DISCRETE NXP Lead Times
6-12 wks
POWER NXP Allocation Heavy allocation
POWER STMicroelectronics Heavily constrained
POWER Vishay Lead Times
16-22 wks
POWER Fairchild Lead Times
30 wks
OPTOCOUPLERS Fairchild Lead Times
8-16 wks
OPTOCOUPLERS Sharp Lead Times
16-22 wks
OPTOCOUPLERS Toshiba Lead Times
16-22 wks
OPTOCOUPLERS Vishay Lead Times
6-8 wks
OPTOCOUPLERS Avago Lead Times
6-8 wks



 

Semiconductors - Memory


 

Supplier Technology Lead Time Price Comments
Atmel EEPROM (Serial) Serial EEPROM price stable, issues on 512k and extending Lead Times on 16k
Atmel EEPROM (Parallel & Wireless) Price remains stable
Atmel EPROM Lead Times remain stable at between ex-stock to 8 wks depending on density
Atmel Flash 4-16 wks Lead Times no major issues
Cypress Slow SRAM Improvement in general Lead Times due to new die and production mix.
Cypress Fast SRAM Improvement in general Lead Times due to new die and production mix. Issues still on 2Mb and 4Mb
IDT Fast SRAM
26 wks
Intel Flash
4-8 wks
Microchip EEPROM Lead Times between
4-16 wks
Micron SDRAM
4-6 wks
Micron DDR I and DDR II 16 wks to allocation Mixed availability on parts
Micron NAND Flash Samples and pre-production volumes only
NEC SRAM
Lead Times 16 wks
Renesas SRAM
Lead Times 16 wks
Samsung Fast SRAM 4Mb IndTemp still ok, full production.
Samsung SDRAM Allocation Parts on allocation upside available dependant on density and Samsung production mix
Samsung DDR I and DDR II 256Mb & 512Mb average Lead Times 4-6 wks,
1Gb 8-10 wks
Samsung NAND Flash None left on allocation, rest on average 7-9 wks.
Sharp SRAM (64k Only) EOL On EOL now.
Spansion Flash No major supply issues Lead Times 4-16 wks dependant on density and package
STMicroelectronics EEPROM Lead Times now 4-16 wks
STMicroelectronics EPROM No major supply issues Lead Times 4-16 wks dependant on density and package
STMicroelectronics NOR Flash Lead Times 4-16 wks no major supply issues
STMicroelectronics NAND Flash Focus on 128Mb, 256Mb and 512Mb Joint venture with Hynix. New for distribution customers
Toshiba SRAM Obsolete All SRAMs which were left are EOL'd
Toshiba NAND Flash Allocation Parts in short supply, EOL on 64Mb and 128Mb Price trends dependant on density



 

Semiconductors - Proprietary


 

Supplier Technology Lead Time Price Comments
Analog Devices Analogue Yield issues on some specific Part Numbers. Lead Times typically
12-16 wks overall.
Some parts on formal allocation.
Military parts 22 wks
Analog Devices DSP Yield issues on some specific Part Numbers. Lead Times typically
12-16 wks overall.
Some parts on formal allocation
Altera FPGA Some Stratix II and Max II still on allocation.
Lead time typically
6-12 wks
Atmel AVR-Micro's, (ATMEGA, ATTINY) AVR's 8-12 wks,
C51 core 16-18 wks
Cypress Low speed USB Lead Times 6-14 wks
Cypress HOTLinkII (parts beginning CYP, CYV, CYW) Lead Times appr.
6-8 wks
Cypress Low speed USB Lead Times appr.
18-20 wks
Freescale 8-bit &16-bit Micros with embedded Flash Generally 8-bit and 16-bit Flash MCU's Lead Times 22-26 wks due to increased demand. Improvement expected in Q1'07 to be 14-16 wks
IR Power Capacity problems on DPAK, SO8 and D2PAK. Lead Times 22-26 wks
LTC Data Converters Lead Times typically 4 wks
LTC Amplifiers / Comparators Lead Times typically 4 wks
LTC Power Management Lead Times typically 4 wks
LTC Interface Lead Times typically 4 wks
Micrel Ethernet (KSx) High Bandwidth (SYx) Lead Times 6-16 wks
STMicroelectronics Regulator: Ppak and D2pak Lead Times 20 wks+
STMicroelectronics Rectifiers Lead Times 15-20 wks
STMicroelectronics Protection Lead Times 11-15 wks
Texas
Instruments
High Performance Analogue INAx, OPAx, Ucx Allocation Test capacity & qualifying issues. Old legacy Burr Brown parts on formal allocation and Lead Times on others still extended at 12-26 wks
Texas
Instruments
TMS320 - DSP's Lead Times are improving between 12-16 wks
Texas
Instruments
MSP430 - Micro's Lead Times are improving between 12-16 wks



 

Displays


 

Supplier Technology Lead Time Price Comments
Sharp Displays Allocation Extended Lead Times between 22-26 wks
All Displays General Lead Times between 12-16 wks on Far East Suppliers.



 

PEMCO - Passives


 

Product Package Lead Times Price Comments
Ceramic Capacitors Surface Mount Murata high-caps extended Lead Times
Ceramic Capacitors Leaded
Lead Times 12 wks
Tantalum Capacitors Surface Mount Kemet High-caps Lead Times up to 35 wks
Tantalum Capacitors Leaded Lead Times 10 wks
Film Capacitors Box BCC film caps
Lead Times 22 wks
Electrolytic Capacitors Small Can BCC Alu caps
Lead Times 22 wks
Electrolytic Capacitors Large Can
Lead Times 18 wks
Resistors Surface Mount Yageo PR/PF,RC0805,RC1206 Lead Times increased to 15 wks
Resistors Leaded Lead Times 10 wks
Inductors  
Lead Times 10 wks
Crystals Surface Mount Lead Times 10 wks
Crystals Leaded Lead Times 10 wks
Fuses Standard   Littelfuse parts have a general Lead Time increase by 2 wks
Fuses Surface Mount Lead Times 10 wks
Fuses Resettable
Lead Times 10 wks



 

PEMCO - Connectors


 

Supplier Technology Lead Time Trend Price Trend Comments
3M Headers,
IDC,
Cable/B-Board, Sockets
Headers 3-8 wks
IDC 8-14 wks
Cable/B board
6-12 wks
Sockets 8 wks.
Some overdue delivery issues
Samtec Headers,
IDC,
Cable/B-Board,
Sockets
Standard Lead Times
3 weeks
Tyco Headers,
IDC,
Cable/B-Board,
Sockets
Headers 9-18 wks
IDC 9-18 wks
Cable/B board
9-20 wks
Sockets 12-22 wks.
Molex Headers,
IDC,
Cable/B-Board,
Sockets
Headers 10-14 wks
IDC 7-15 wks
Cable/B board
11-16 wks
Sockets 8 wks.
Lead Times now stabilising.
FCI Headers,
IDC,
Cable/B-Board,
Sockets
Headers 9-12 wks
IDC 10 wks
Cable/B board
8-12 wks
Sockets 10 wks.
FCI I/O,
Modular,
D-Sub
I/O 5-14 wks
D-sub 10-14 wks
Molex I/O,
Modular,
D-Sub
I/O 5-12 wks
D-sub 5-10 wks
Samtec I/O,
Modular,
D-Sub
Standard Lead Times 3 weeks
Tyco Power,
Terminal Blocks,
Industrial
Power 7-19 wks
Terminal blocks
9-20 wks
Industrial 7-16 wks.
Tyco
RF Connectors

18-20 wks



 

PEMCO - Electromechanical


 

Supplier Technology Lead Time Trend Price Trend Comments
Omron General purpose Relays
Signal
Telecom
General purpose Relays /Signal / Telecom /
16 wks (may have stock at Omron, please check with Arrow)
Tyco General purpose Relays
Signal
Telecom
General purpose Relays 8-24 wks
Signal and Telecom 6-18 wks.
Some Relays lead times going out 12 to 24 wks due to high demand.
Fujitsu General purpose
PCB Relays
Average lead time 14-18 wks.
Increase on FTR-B3 / B4 range also JS relays all now quoting 24 wks with possible future allocation
Knitter Switch DIL switches
Lever
Toggle
Tactile
Pushbutton
DIL switches
6-7 wks
Lever / Toggle
6-14 wks
Tactile 6-8 wks
Pushbutton 6-14 wks
ITT Cannon DIL switches
Lever
Toggle
Tactile
Pushbutton
DIL switches
7-14 wks
Lever
Toggle 6-15 wks
Tactile 6-8 wks
Pushbutton 6-18 wks.



 

Power Supplies


 

Supplier Technology Lead Time Trend Price Trend Comments
Astec Power supplies
DC-DC Converters
15-17 wks Lead Times. Astec have bought Artesyn, still trading as separate names.
CD Power supplies
DC-DC Converters
9-18 wks extending. Continuing extended Lead Times


 

 

 

 

Legend:

Increasing

Stable

Decreasing


Last updated: 15th January 2007

 
Semiconductors - Standard Products

 
Technology Supplier Lead Time Price Comments
LOGIC Fairchild Lead Times reduced to
8-12 wks
LOGIC NXP Lead Times 8-12 wks
LOGIC ON Semiconductor Lead Times 8-12 wks. Price differential on leaded Vs RoHS compliant
LOGIC STMicroelectronics Off formal allocation. Lead Times 12-18 wks
LOGIC Texas Instruments Lead Times 6-12 wks
LINEAR National Semiconductor  
LINEAR STMicroelectronics Allocation Allocation but anticipate recovery through Q1'07
LINEAR Texas Instruments Lead Times 6-12 wks.
LINEAR Toshiba  
LINEAR ON
Semiconductor
 
LINEAR Vishay Lead Times
22-26 wks
DISCRETE ON
Semiconductor
Lead Times
8-12 wks
DISCRETE Vishay Lead Times
12-16 wks
DISCRETE Taiwan Semi Lead Times
12 wks
DISCRETE STMicroelectronics Lead Times
12-16 wks
DISCRETE NXP Lead Times
8-12 wks
POWER NXP Allocation Heavy allocation
POWER STMicroelectronics Heavily constrained
POWER Vishay Capacity constrained with severe delinquencies
POWER Fairchild Lead Times increased to 22-26 wks
OPTOCOUPLERS Fairchild Lead Times 8-16 wks
OPTOCOUPLERS Sharp Lead Times 16-22 wks
OPTOCOUPLERS Toshiba Lead Times 16-22 wks
OPTOCOUPLERS Vishay Lead Times 16-22 wks


 
Semiconductors - Memory

 
Supplier Technology Lead Time Price Comments
Atmel EEPROM (Serial) Serial EEPROM price stable, issues on 512k and extending Lead Times on 16k
Atmel EEPROM (Parallel & Wireless) Price remains stable
Atmel EPROM Lead Times remain stable at between ex-stock to 8 wks depending on density
Atmel Flash Lead Times
4-16 wks
Cypress Slow SRAM Improvement in general Lead Times due to new die and production mix.
Cypress Fast SRAM Improvement in general Lead Times due to new die and production mix. Issues still on 2Mb and 4Mb
IDT Fast SRAM Lead Times
26 weeks
Intel Flash Lead Times
4-16 wk
Microchip EEPROM Lead Times between
8-10 wks
Micron SDRAM Lead Times
4-16 wks
Micron DDR I and DDR II 16 wks to allocation Mixed availability on parts
Micron NAND Flash Samples and pre-production volumes only
NEC SRAM Lead Times
16 wks
Renesas SRAM Lead Times
16 wks
Samsung Fast SRAM 4Mb IndTemp still ok, full production. 1Mb all and 4Mb Com-temp discontinued, causing supply issues for the rest of the market. SyncSRAM are 12-20 wks Lead Times, RoHS still limited availability
Samsung SDRAM Average Lead Times 6-8 wks
Samsung DDR I and DDR II 256Mb & 512Mb average Lead Times 4-6 wks, 1Gb 8-10 wks
Samsung NAND Flash None left on allocation, rest on average 7-9 wks.
Sharp SRAM (64k Only) EOL On EOL now.
Spansion Flash No major supply issues Lead Times 4-16 wks dependant on density and package
STMicroelectronics EEPROM Lead Times now 4-16 wks
STMicroelectronics EPROM  
STMicroelectronics NOR Flash Lead Times 4-16 wks No major supply issues
STMicroelectronics NAND Flash Focus on 128Mb, 256Mb and 512Mb Joint venture with Hynix. New for distribution customers
Toshiba SRAM Obsolete All SRAMs which were left are EOL'd
Toshiba NAND Flash Allocation Parts in short supply, EOL on 64Mb and 128Mb Price trends dependant on density


 
Semiconductors - Proprietary

 
Supplier Technology Lead Time Price Comments
Analog Devices Analogue Yield issues on some specific Part Numbers. Lead Times typically 12-16 wks overall. Some parts on formal allocation. Military parts 22 wks
Analog Devices DSP Yield issues on some specific Part Numbers. Lead Times typically 12-16 wks overall. Some parts on formal allocation
Altera FPGA Some Stratix II and Max II still on allocation. Lead time typically 6-12 wks
Atmel AVR-Micro's, (ATMEGA, ATTINY) AVR's 8-12 wks, C51 core 16-18 wks
Cypress Low speed USB Lead Times 6-14 wks
Cypress HOTLinkII (parts beginning CYP, CYV, CYW) Lead Times appr. 6-8 wks
Cypress Low speed USB Lead Times appr. 18-20 wks
Freescale 8-bit &16-bit Micros with embedded Flash Generally 8-bit and 16-bit Flash MCU's Lead Times 22-26 wks due to increased deamand. Improvement expected in Q1'07 to be 14-16 wks
IR Power Capacity problems on DPAK, SO8 and D2PAK. Lead Times 22-26 wks
LTC Data Converters Lead Times typically 4 wks
LTC Amplifiers / Comparators Lead Times typically 4 wks
LTC Power Management Lead Times typically 4 wks
LTC Interface Lead Times typically 4 wks
Micrel Ethernet (KSx) High Bandwidth (SYx) Lead Times 6-16 wks
STMicroelectronics Regulator: Ppak and D2pak Lead Times 20 wks+
STMicroelectronics Rectifiers Lead Times 15-20 wks
STMicroelectronics Protection Lead Times 11-15 wks
Texas Instruments High Performance Analogue INAx, OPAx, Ucx Test capacity & qualifying issues. Most Lead Times between 22-26 wks
Texas Instruments TMS320 - DSP's Lead Times are improving between 12-16 wks
Texas Instruments MSP430 - Micro's Lead Times are improving between 12-16 wks


 
Displays

 
Supplier Technology Lead Time Price Comments
Sharp Displays Allocation Extended Lead Times between 22-26 wks
All Displays General Lead Times between 12-16 wks on Far East Suppliers.


 
PEMCO - Passives

 
Product Package Lead Times Price Comments
Ceramic Capacitors Surface Mount Murata high-caps extended Lead Times
Ceramic Capacitors Leaded Lead Times
12 wks
Tantalum Capacitors Surface Mount Kemet High-caps Lead Times up to 35 wks
Tantalum Capacitors Leaded Lead Times 10 wks
Film Capacitors Box BCC filmcaps Lead Times 22 wks
Electrolytic Capacitors Small Can BCC Alu caps Lead Times
22 wks
Electrolytic Capacitors Large Can Lead Times
18 wks
Resistors Surface Mount Yageo PR/PF,RC0805,RC1206 Lead Times increased to 15 wks
Resistors Leaded Lead Times
10 wks
Inductors   Lead Times
10 wks
Crystals Surface Mount Lead Times
10 wks
Crystals Leaded Lead Times
10 wks
Fuses Standard Littelfuse parts have a general Lead Time increase by 2 wks
Fuses Surface Mount Lead Times
10 wks
Fuses Resettable Lead Times
10 wks


 
PEMCO - Connectors

 
Supplier Technology Lead Time Trend Price Trend Comments
3M Headers, IDC, Cable/B-Board, Sockets Headers 3-4 wks / IDC 6 wks / Cable/B board 6-12 wks
Samtec Headers, IDC, Cable/B-Board, Sockets Standard Lead Times 3 wks
Tyco Headers, IDC, Cable/B-Board, Sockets Headers 9-22 wks / IDC 20 wks / Cable/B board 20 wks / Sockets 20 wks. Price increase January 07
Molex Headers, IDC, Cable/B-Board, Sockets Headers 9-20 wks / IDC 9-20 wks / Cable/B board 10-12 wks /Sockets 14 wks
FCI Headers, IDC, Cable/B-Board, Sockets Headers 6-9 wks / IDC 9-19 wks / Cable/B board 8-10 wks /Sockets 10 wks
FCI I/O, Modular, D-Sub I/O 5-14 wks / D sub 10-12 wks
Molex I/O, Modular, D-Sub I/O 5-12 wks / D sub 5-12 wks
Samtec I/O, Modular, D-Sub Standard Lead Times 3 wks
Tyco Power, Terminal Blocks, Industrial Terminal blocks 9-29 wks / Industrial 12-20 wks
Tyco RF Connectors Lead Times
9-24 wks


 
PEMCO - Electromechanical

 
Supplier Technology Lead Time Trend Price Trend Comments
Omron General purpose Relays /Signal / Telecom General purpose Relays /Signal / Telecom / 16 wks
Tyco General purpose Relays /Signal / Telecom General purpose Relays 10-12 wks / Signal and Telecom 6-18 wks. Some Lead Times increased to 28 wks on 4G and IM relays possible allocation
Knitter-switch DIL switches / Lever /Toggle /Tactile/ Pushbutton DIL switches 8-10 wks / Lever / Toggle 8 wks/ Tactile 6-8 wks /Pushbutton 8-24 wks
ITT Cannon DIL switches / Lever /Toggle /Tactile/ Pushbutton DIL switches 8 wks / Lever / Toggle 6-15 wks/ Tactile 6-8 wks/ Pushbutton 6-18 wks
Fujitsu (Nordic only) General purpose Relays General purpose Relays 11-14 wks


 
PEMCO - Power Supplies

 
Supplier Technology Lead Time Trend Price Trend Comments
Astec Power Power supplies /DC-DC Converters 8-23 wks Lead Times
C&D Technologies Power supplies /DC-DC Converters 10-18 wks extending.

 

 

 

Sept 2006

Click here.

 

June 2006

Legend:
Increasing
Stable
Decreasing

 

Semiconductors - Standard Products


 
Technology Supplier FAB Capacity Lead Time Price Comments
LOGIC Fairchild 95% Lead Times 24-30 wks. FSC booked out for Q4. Price increases expected Q3.
LOGIC Philips 95% Lead Times 20-30 wks. Philips added capacity but insufficient to meet demand. Price increases expected Q3.
LOGIC ON Semiconductor 80%  
LOGIC STMicroelectronics 100% Allocation Allocation. Price increases expected Q3.
LOGIC Texas Instruments 90%   Lead Times vary from 12-26 wks. Price increases expected Q3.
LINEAR National Semiconductor 95%  
LINEAR STMicroelectronics 100% Allocation Q3 allocation loaded, no opportunity to book upside. Will definitely increase price Q3.
LINEAR Texas Instruments 95% Lead Times vary from 18-26 wks. TLC range just increased from 12-26 wks. Price increase expected Q3 5%+.
LINEAR Toshiba 80%  
LINEAR ON Semiconductor 90% Lead Times increasing. Q2 interim price increases issued on Regulators.
LINEAR Vishay 95% Lead Times increasing to 22-26 wks minimum.
DISCRETE ON Semiconductor 95% Allocation on SOD123 / SOT23 high runners. Price increase expected Q3.
DISCRETE Vishay 95% Lead Times 16 wks+ and increasing. Unable to get confirmations. Price increases on small signal expected Q3.
DISCRETE Taiwan Semi 95% Lead Times 20 wks+.
DISCRETE STMicroelectronics 95% Rectifiers, protection, Bipolar Lead Times all moving out to 16 wks+. Focus discrete supplier to Arrow.
DISCRETE Philips 90%+ Lead Times increasing to 12-24 wks. Philips are booked out for Q4; potential ALLOCATION. Global demand at an all time high.
POWER Philips 100% Allocation Heavy allocation. Not confirming orders until 2007.
  STMicroelectronics 95% Lead Times increasing to 16-22 wks+.
POWER Vishay 95% Capacity constrained with severe delinquencies.
POWER Fairchild 95% Lead Times increased to 22-26 wks. FSC booked out Q4.
OPTOCOUPLERS Fairchild 90% Lead Times increasing and FSC booked out through Q4.
OPTOCOUPLERS Sharp 100%   Off allocation; Lead Times 22 wks. Excellent position on inventory and backlog.
OPTOCOUPLERS Toshiba 95% High demand with extending Lead Times.
OPTOCOUPLERS Vishay 90% High demand with extending Lead Times.


 

Semiconductors - Memory


 
Supplier Technology FAB Capacity Lead Time Price Comments
Atmel EEPROM (Serial) 90% Serial EEPROM price stable, issues on 512k and extending Lead Times on 16K.
Atmel EEPROM (Parallel & Wireless) 90% Price increase on Parallel.  
Atmel EPROM 85% Lead Times remain stable at between ex-stock to 8 wks depending on density.
Atmel Flash 90% Issues on 32Mb, 64Mb and 512k due to die shrinks and increase orders from mobile phone manufactures.
Cypress Slow SRAM 100/90% Allocation All older die revisions on allocation, will continue for Q3. Once new die's released, old going EOL. Shipping 4Mb uPower (CY6214xExx and CY62), 1 & 8Mb just released, 2 & 16Mb Q3 and 256k Q2'07. New die rev Lead Times ~8-14 wks.
Cypress Fast SRAM 100/90% Allocation Allocation as with slow SRAM, new dies 64/256/512k, 1/2/4/8Mb releasing now, 16Mb Q4, only exception 256k CY7C1399 Q2'07. New 5V pricing increased on 4Mb, 1Mb, 3V on both 1 & 4Mb. New die rev Lead Times ~8-14 wks.
IDT Fast SRAM 95% 8 to 16 wks.
Intel Flash 100% Allocation Issues with J3D support, 128Mb major issues manual allocation, P30 should be now more than 16 wks.
Microchip EEPROM 85% No major changes in price or availability, Lead Time between 8-10 wks.  
Micron SDRAM 90% to 95% Allocation 128Mb still allocation, 64Mb announced just joining.
Micron DDR I and DDR II 90% to 95%  
Micron NAND Flash 100% Samples and pre-production volumes only.
NEC SRAM 90% to 95%  
Renesas SRAM 90% to 95%  
Samsung Slow SRAM 100% EOL All K6X and 1 & 2Mb K6F on EOL, LTB June, LTD October. All new orders quoting 10-12 mth Lead Time, they are fully booked on EOL types and no short term help seen.
Samsung Fast SRAM 95% 4Mb IndTemp still ok, full production. 1Mb all and 4Mb Com-temp discontinued, causing supply issues for the rest of the market. SyncSRAM are 12-20 wks Lead Time, RoHS still limited availability.
Samsung SDRAM 90% Average Lead Time 4-6 wks.
Samsung DDR I and DDR II 90% 256 & 512Mb average Lead Time 4-6 wks, 1Gb 8-10 wks.
Samsung NOR Flash 90%  
Samsung NAND Flash 85% None left on allocation, rest on average 7-9 wks. Pricing stable, some densities with minor decrease.
Sharp SRAM (64k Only) 90% to 95% EOL On EOL now. 
Sharp Flash 95% Lead Time currently 24 wks+. Only supporting 3V parts. 5V EOL Dec'05.
Spansion Flash 90%+ Now acknowledging all PLCC parts for delivery on new orders November, 5V parts Lead Time increasing due to automotive OEM customer demand. 64Mb now on 20 wks. Predict allocation by end of September.
STMicroelectronics EEPROM 85% Lead Times now 18 wks for new orders.
STMicroelectronics EPROM 85%  No real changes in supply or price in recent quarters.
STMicroelectronics NOR Flash 90% 64Mb on 16 wks, price increases in Q3 Lead Times extending.  
STMicroelectronics NAND Flash 90% Focus on 128Mb, 256Mb and 512Mb. Joint venture with Hynix. New for distibution customers.
Toshiba SRAM 90% Obsolete All SRAMs which were left are EOL'd.
Toshiba NOR Flash 90%  
Toshiba NAND Flash 100% Allocation Parts in short supply, EOL on 64Mb and 128Mb. Price trends dependant on density


 

Semiconductors - Proprietary


 
Supplier Technology FAB Capacity Lead Time Price Comments
Analog Devices Analogue n/a Yield issues on some specific Part Numbers. Lead Times typically 12-16 wks overall. Some parts on formal allocation.
Analog Devices DSP   Yield issues on some specific Part Numbers. Lead Times typically 12-16 wks overall. Some parts on formal allocation.
Altera FPGA 100% Allocation Capacity problem at TSMC. Allocation should be over early Q3 '06.
Atmel AVR-Micro's, (ATMEGA, ATTINY) 90% 18-20 wks, due to capacity problem with test and assembly. Atmel moved their testing from San Jose facility to Taiwan. Should be stabilised mid Q2 '06.
Cypress Low speed USB 90% - 95% Lead Times 13-16 wks. Current projection is Lead Times will stabilise in Q3 '06.
Cypress HOTLinkII (parts beginning CYP, CYV, CYW) 100% Lead Time appr. 18-20 wks. Other suppliers stopped producing these products and therefore ramp up at Cypress. Estimation for extended delivery to remain until end of Q3 '06.
Cypress Low speed USB 90% - 95% Lead Times 13-16 wks. Current projection is Lead Times will stabilise in Q3 '06.
Freescale 16-bit Micros with embedded flash 100% Allocation Allocation due to manufacturing problem related to their partner TSMC3. Allocation should be over by end Q3 '06. Generally all Freescale Lead Times are extended. Major impact into Automotive applications
IR Power 90% +   Capacity problems on DPAK Packaging.
LTC Data Converters n/a Lead Times typically 4 wks
LTC Amplifiers / Comparators n/a Lead Times typically 4 wks.
LTC Power Management n/a Lead Times typically 4 wks
LTC Interface n/a Lead Times typically 4 wks.
Micrel Ethernet (KSx) High Bandwidth (SYx) 95% Off Allocation, Lead Times 18-24 wks.
STMicroelectronics Regulator: Ppak and D2pak 100% Allocation Allocation.
STMicroelectronics Interface: SO16 packages. 100% Allocation ST operating almost on full capacity. Mainly driven by AsiaPac market. Also capacity problem in test & assembly.
STMicroelectronics Linear: MiniSO, SO14 and SO8 100% Allocation ST operating almost on full capacity. Mainly driven by AsiaPac market. Also capacity problem in test & assembly.
Texas
Instruments
High Performance Analogue INAx, OPAx, Ucx 90% + Test capacity & qualifying issues.
Texas
Instruments
TMS320 - DSP's 90% + Test capacity issues.
Texas
Instruments
MSP430 - Micro's 100% Contamination of wafers at FAB (TSMC) - all scrapped & re-started - some backlog now re-confirmed to Sept '06.


 

Displays


 
Supplier Technology FAB Capacity Lead Time Price Comments
Sharp Displays 100% Allocation Extended Lead Times between 22-26 wks.
All Displays 80% - 90% General Lead Times between 12-16 wks on Far East suppliers. ROHS conversion slow.


 

PEMCO - Passives


 
Product Package Current Lead Time Lead Time Price Comments
Ceramic Capacitors Surface Mount 12 wks  
Ceramic Capacitors Leaded 10 wks  
Tantalum Capacitors Surface Mount 9 wks  
Tantalum Capacitors Leaded 12 wks  
Film Capacitors Box 11 wks  
Electrolytic Capacitors Small Can 13 wks  
Electrolytic Capacitors Large Can 13 wks  
Resistors Surface Mount 12-15 wks Yageo PR/PF,RC0805,RC1206 Lead Times increase to 15 wks.
Resistors Surface Mount - Phycomp Allocation Forecasted to be off Allocation end Q3 '06
Resistors Leaded 10 wks Vishay price increases
Inductors   10-16 wks  
Crystals Surface Mount 10 wks Significant Lead Time issues with Raltron. Cross reference to TXC or CMAC.
Crystals Leaded 9 wks Significant Lead Time issues with Raltron. Cross reference to TXC or CMAC.
Fuses Standard 12 wks  
Fuses Surface Mount 10 wks  
Fuses Resettable 9 wks  


 

PEMCO - Electro-Mechanical


 
Supplier Technology  Lead Time Trend Price Trend Comments
Omron General purpose Relays /Signal / Telecom General purpose Relays /Signal / Telecom / 16 wks (may have stock at Omron).
Tyco General purpose Relays /Signal / Telecom General purpose Relays 8-12 wks. Signal and Telecom 6-18 wks.
Knitter-switch DIL switches / Lever /Toggle /Tactile/ Pushbutton DIL switches 6-7 wks. Lever / Toggle 6-14 wks. Tactile 6-8 wks. Pushbutton 6-14 wks.
ITT Cannon DIL switches / Lever /Toggle /Tactile/ Pushbutton DIL switches 7-14 wks. Lever / Toggle 6-15 wks. Tactile 6-8 wks. Pushbutton 6-18 wks *ROHS issues, not all parts available. Price increase in April 4-6%.


 

PEMCO - Connectors


 
Supplier Technology Lead Time Trend Price Trend Comments
3M Headers, IDC, Cable/B-Board, Sockets Headers 3-8 wks. IDC 8-14 wks. Cable/B-Board 6-12 wks. Sockets 8 wks.
Samtec Headers, IDC, Cable/B-Board, Sockets All products are high demand with capacity issues.
Tyco Headers, IDC, Cable/B-Board, Sockets Headers 9-18 wks. IDC 9-18 wks. Cable/B-Board 9-20 wks. Sockets 12-22 wks. Another Price Increase approx 5% 01/07/06.
Molex Headers, IDC, Cable/B-Board, Sockets   Headers 10-14 wks. IDC 7-15 wks. Cable/B-Board 11-16 wks. Sockets 8 wks. Lead Times extending but no 'official' change by Molex.
FCI Headers, IDC, Cable/B-Board, Sockets Headers 9-12 wks. IDC 10 wks. Cable/B-Board 8-12 wks. Sockets 10 wks. Price increased between 2-6% in May 06.
FCI I/O, Modular, D-Sub I/O 5-14 wks. D-Sub 10-14 wks.
Molex I/O, Modular, D-Sub     I/O 5-12 wks. D-Sub 5-10 wks.
Samtec I/O, Modular, D-Sub     All products are high demand with capacity issues.
Tyco Power, Terminal Blocks, Industrial     Power 7-19 wks. Terminal blocks 9-20 wks. Industrial 7-16 wks.
Tyco RF Connectors     18-20 wks.


 

PEMCO - Power Supplies


 
Supplier Technology Lead Time Trend Price Trend Comments
Astec Power supplies /DC-DC Converters 15-17 wks Lead Time.
C&D
Technologies
Power supplies /DC-DC Converters 9-18 wks extending. ROHS parts now available.


 

 

January 2005

Semiconductors

Micro - Standard lead-time approx. 16 weeks. Renesas - 16 Bit Micro ON ALLOCATION. TI  offer a 2 week delivery

Memory - Standard lead-time approx. 26 weeks. Maxim & STM – 14/16 weeks. BEWARE – Some STM is ON ALLOCATION

Commodity Lin & Logic - Maxim & Rohm – 14 weeks +. BEWARE – Some STM is ON ALLOCATION. Standard Lead-time approx. 4-8 weeks

Non-Commodity Lin & Logic - Standard Lin & Logic between 12-16 weeks. FSC can be as long as 20 weeks 

Discretes - Infineon & STM are best at approx. 10 weeks. FSC not good at 20 + weeks. All the rest 12-16 weeks

Passives

Electrolytics - Standard lead-time approx. 12-14 weeks. Epcos best of the bunch at only 10 weeks

Tantalums - Lead-times all over the place on Tants with variants from 5-26 weeks. AVX at 5-7 weeks. Vishay at 10-19 weeks. Arcotronics at 26 weeks

Cap Ceramics - Again Big variations on lead-time (Range from 6-26 weeks) Kemet & Epcos at only 6-8 weeks. Arcotronics at 26 weeks. The rest sit at around 12-16 weeks

Inductors - Lead-times approx. 10-12 weeks. AVX & TDK at only 9 weeks. Tyco at 14 weeks 

Fuses - Bourns resettable fuses at 9 weeks. Littelfuse at 14 weeks

Resistors - Standard lead-time approx. 10 weeks. Rohm at only 8-9 weeks

Emech

D Type - Average lead-time is at approx. 8 weeks. Schurter can offer as low as 4 weeks

Pin Headers - 3M can offer 4 weeks. Average lead-time is approx. 8 weeks

Switches & Relays - Crydom at 6 weeks. Omron at 16 weeks. Average lead-time 10-14 weeks

Cable - Lead-times vary from 3-10 weeks. 3M at 3 weeks. Hirose & Tyco out at 8-10 weeks

Fans - All Fans available on 10-12 week lead-time

 

November 2004

Semiconductors

Micro - Standard lead-time approx. 16 weeks. Renesas - 16 Bit Micro ON ALLOCATION

Memory - OKI at 26 weeks. Some ST & Toshiba ON ALLOCATION. ALL Renesas SRAM’s ON ALLOCATION.

Commodity Lin & Logic - Texas Inst. - 3 weeks. Infineon & NSC - 8 weeks. Fairchild & Rohm - 12 weeks +. BEWARE - Some STM is ON ALLOCATION. Standard Lin & Logic between 12-16 weeks

Non- Commodity Lin & Logic - Lead-time ranges from 12-16 weeks. National ahead of the rest at only 8 weeks. 

Discretes - Standard lead-time approx. 12 weeks. Fairchild currently at around 20 weeks

Passives

Electrolytics - Standard lead-time approx. 14-16 weeks. BHC at 8-12 weeks. Epcos at 10 weeks.

Tantalums - Lead-times all over the place on Tants with variants from 5-26 weeks. AVX at 5-7 weeks Epcos, Kemet & Rohm at approx. 10 week. Vishay at 19 weeks and Arcotronics at 26 weeks.

Inductors - Lead-times approx. 10 weeks. Tyco currently at 14 weeks

Resistors - Standard lead-time approx. 10 weeks. Bourns at 14 weeks. Tyco ranges from 8-16 weeks

Cap Ceramics - Again big variations on lead-time (from 6-26weeks) Kemet at 6-8 weeks AVX, Epcos & Panasonic at around 12 weeks Murata, Rubycon & TDK at around 16 weeks. Arcotronics at 26 weeks.

Emech

Most Product Types running with a lead-time of around 8 weeks Some Exceptions: Omron at 16 weeks Tyco & Hypertac up to 14 weeks. Batteries and Cable Product available in around 6 weeks, except for Hirose & Tyco at 8-10 weeks

 


 March 2004

Last Update
March 2004
Lead times In Weeks Price Action / Comment
Product Package / Family Today vs Previous
 Month
Forward Current

Forward
Trend

 
  SOT23 24 Please schedules asap beyond current qtr
SMB TVS 18-24 Please schedules asap beyond current qtr
TO-220 2N 12-16
Please schedules asap beyond current qtr
SOD80 12-14 Please schedules asap beyond current qtr
SMA / SMC TVS 16-18 IR/FSC/ST most affected
P

O

W

E

R

O220 / 247 16-30 IR/FSC/ST/ON most affected
DPAK / D2PAK 14-36  
ISOTOP / ISOWATT 10-14 Stable Long lead time with ST on the TSSOP package. OnSemi has lead times on some devices are going up to 15 weeks. Philips have some long lead time on some specific product on the 74HC.
L

O

G

I

C

CMOS 5v 4000/HC/HCT 4-15 Stable Call factory with ST on TSSOP package. 15 weeks delivery on the 74AC245DWR2 with OnSemi…11 weeks delivery with FSC on some specific parts.
CMOS 5v AC/ACT/FCT 6-11 Stable Stable Lead time starting to increase depending on product … / TSSOP package are on call factory
BiCMOS ABT 8-10 Starting to increase Stable Stable Stable Stable
Adv CMOS 3v LVC/LVT 4-11 Stable Stable Stable Standard analog parts are virtual allocation with NSC
L

I

N

E

A

R

NSC 14-16 NSC and PHI situation are causing price and lead time increases here
ONSEMI 14-16 Stable  
SIPEX 10-12 Stable Stable Stable Affected to a lesser degree….so far……
MICREL 10-12 NSC and PHI situation are causing price and lead time increases here
ST 10-12  
FAIRCHILD 10-12 Lead-times gone out to Fab move
O

P

T

O

FAIRCHILD 26-30 26-30 Stable Stable  
VISIBLE OPTO 8-10 Stable Stable Stable Stable  
FIBRE OPTICs 8-10 Stable Stable Stable Stable  
INFRA RED 8-10 Stable Stable Stable Stable  

 


Jan 2004

Allocation and shortages will hit in early 2004

Microchip.. A letter from the president

The electronics industry is currently experiencing some growing pains.
Increased demand for consumer electronics, PCs and telecom equipment has driven significant growth in
global demand for electronic components through the second half of 2003, and into 2004. Although the UK market has not benefited directly from this growth as much of this type of equipment is now manufactured abroad, we are of course still part of and subject to global market shifts, and resulting trading conditions.

The fundamental issue the industry faces currently is a lack of test and assembly (or "back end") capacity. This lack of capacity has led to a number of product types going on extended lead time and allocation in the past 2weeks.
Semiconductor manufacturers are having to buy additional capacity at a cost which has led to SIGNIFICANT PRICE INCREASES.

In particular we have seen price increases from the following suppliers

National - up to 100% price increase on selected commodity linear parts.
Texas - up to 50% price increase on selected commodity linear parts
Infineon - up to 10% price increases on selected discrete parts
Fairchild - up to 15% price increases on selected discrete parts
STM - have not increased prices on allocation parts as yet, but it seems likely that they will have to increase when they renew their Master Quote in April.

We can protect ourselves against increasing lead times by placing extended orders on our suppliers, but there is little we can do to protect ourselves against price increases.

Please note that some of these price increases will start to impact us in March as new stock comes in at higher prices. Our operations and marketing teams are currently running price checking reports, and trying to negotiate better pricing on affected parts to support contract customers.

At the minute the number of parts affected by this is in the low 100's, however, if history is anything to go by, then the knock on effect is that the number of parts affected will increase dramatically.